Construction Industry Development Board Act, 2000 (Act No. 38 of 2000)Board NoticesStandard for Uniformity in Construction Procurement Published in terms of the Construction Industry Development Board Act, 2000AnnexuresAnnex I : Selection of subcontractors by employers and contractors |
(normative)
Insert the following in the Scope of Work:
Scope of mandatory subcontract works
The following portions of the works shall be subcontracted in accordance with the subcontracting procedures described in this scope of work:
………………………….
Subcontracting procedures
The contractor shall advertise and call for competitive tenders in respect of each portion of the works that are required to be subcontracted in terms of the contract in accordance with the relevant provisions of the latest edition of the ClDB Standard for Uniformity in Construction Procurement. The Contract Data in the associated procurement documents shall be based on the .................. (insert title of standard form of subcontract that is to be used), with minimal project specific variations and amendments that do not change their intended usage.
The Employer together with the Contractor shall evaluate the tenders received in accordance with the provisions of the Standard Conditions of Tender contained in Annex F of Standard for Uniformity in Construction Procurement. The evaluation panel shall comprise equal representatives from the Employer and from the Contractor.
The Contractor shall without delay enter into contract with the successful tendering subcontractor based on their accepted tender submission
The Contractor shall remain responsible for providing the subcontracted portion of the works as if the work had not been subcontracted.
Note:
1. | The ClDB Best Practice Guideline Dl, Subcontracting Arrangements, provides guidance on the selection of a suitable form of subcontracts. |
2. | Provision in the Pricing Data should be made for provisional sums for portions of the works that are to be subcontracted in this manner. |