Best Practice Project Assessment Scheme: Standard for Contract Participation Goals for Targeting Enterprises and Labour through Construction Works Contracts

5. Training and Development

 

5.1 Targeted Enterprises

 

Contract participation goals for enterprise development in General Building (GB) and Civil Engineering (CE) classes of works shall be limited to contracts of tender Grade 7 to 9 and shall be undertaken in terms of the cidb Standard for Indirect Targeting for Enterprise Development through Construction Works Contracts.

 

Contract participation goals for enterprise development in classes of works other than General Building (GB) and Civil Engineering (CE) shall be limited to contracts of tender Grade 7 to 9 and shall be undertaken taking cognisance of the cidb Standard for Indirect Targeting for Enterprise Development through Construction Works Contracts.

 

5.2        Targeted Labour

 

Contract participation goals for skills development for skilled- and semi-skilled labour shall be limited to contracts of tender Grade 7 to 9, and shall be undertaken in terms of the cidb Standard for Developing Skills through Infrastructure Contracts.

 

Contract participation goals for unskilled labour shall be limited to on-the-job training to targeted labour to enable such labour to master the basic work techniques required to undertake the work in accordance with the requirements of the contract and in a manner that does not compromise worker health and safety.