Acts Online
GT Shield

Electricity Regulation Act, 2006 (Act No. 4 of 2006)

Regulations

Electricity Regulations on New Generation Capacity, 2011

4. Planning for new generation capacity

 

(1) The integrated resource plan shall—
(a) be developed by the Minister after consultation with the Regulator; and
(b) be published in the Government Gazette by the Minister.

 

(2) The system operator, the NTC and the Regulator shall timeously provide such assistance as the Minister may require for purposes of developing and monitoring the implementation of an integrated resource plan.

 

(3) The Regulator shall, after consultation with the Minister, the system operator and the NTC, make rules relating to the keeping of relevant information, the submission of such information and the rendering of returns by licensees, as required in order to facilitate integrated resource planning.