Acts Online
GT Shield

Labour Relations Act, 1995 (Act No. 66 of 1995)

Notices

Bargaining Council for the Metal and Engineering Industries

Extension of the Consolidated Main Collective Agreement to Non-parties (for the period 1 July 2021 to 30 June 2024)

Part 2

4. Technical Schedules

Schedule E/3

Wage Rates Applicable to Operations Scheduled in Schedule E/3 are Prescribed in Clause 3(a) of Part II of this agreement

Section (b): Installation Section

Subsection (b)(v): Electrical

 

RATE AA

1. Marking out by tape or rule of the centres and working lines of articles and material for erection of cable racks.
2. Modifications to pre-manufactured cable racks.
3. Fixing of cables and/or conduit to cable racks, excluding preparation of leads for fitting of glands.
4. Running of cables, excluding preparation of leads for fitting of glands.
5. Repetition making up of cable harnesses where course of wire is marked by cleats and/or lines and/or saddles and/or fixtures and where no wiring diagram is used.

 

RATE D

1. Erection of pre-manufactured and/or fabricated cable racks and associated articles using tape and/or rule and under supervision of Rate AA employee.
2. Bending of conduits by hand.
3. Repetition crimping of terminals and/or stripping ends of wires.
4. Repetition pulling through only of cables and/or wire pre-cut to predetermined lengths.
5. Installation of control components to predetermined positions.