36. Variation and rescission of rulings and arbitration awards

 

An application for the variation or rescission of an arbitration award or ruling must be made within fourteen (14) days of the date on which the applicant became aware of—

(a) the arbitration award or ruling; or
(b) a mistake common to the parties to the proceedings.