Activity
number
|
Activity description
|
Identification of competent authority
|
1
|
The construction of facilities or infrastructure, including associated structures of infrastructure, for –
a) |
the generation of electricity where the electricity output is more than 10 megawatts but less than 20 megawatts; |
b) |
the above ground storage of 1 000 ton or more but less than 100 000 tons of ore; |
c) |
the storage of 250 tons or more but less than 100 000 tons of coal; |
d) |
resorts, lodges, hotels or other tourism and hospitality facilities in a protected area contemplated in the National Environmental Management: Protected Areas Act, 2003 (Act No. 57 of 2003); |
e) |
any purpose where lawns, playing fields or sports tracks covering an area of more than three hectares, but less than 10 hectares, will be established; |
f) |
sport spectator facilities with the capacity to hold 8 000 spectators or more; |
g) |
the slaughter of animals with a product throughput of 10 000 kilograms or more per year; |
h) |
the concentration of animals for the purpose of commercial production in densities that exceed- |
i) |
20 square metres per head of cattle and more than 500 head of cattle per facility per year; |
ii) |
eight square meters per sheep and more than 1 000 sheep per facility per year; |
iii) |
eight square metres per pig and more than 250 pigs per facility per year excluding piglets that are not yet weaned; |
iv) |
30 square metres per crocodile at any level of production, excluding crocodiles younger than 5 months; |
v) |
three square metres per head of poultry and more than 250 poultry per facility at any time; excluding chicks younger than 20 days; |
vi) |
three square metre per rabbit at and more than 250 rabbits per facility at any time; or |
vii) |
100 square metres per ostrich and more than 50 ostriches per facility per year or 2500 square metres per breeding pair; |
i) |
aquaculture production, including mariculture and algae farms, with a product throughput of 10 000 kilograms or more per year; |
j) |
agri-industrial purposes, outside areas with an existing land use zoning for industrial purposes, that cover an area of 1000 square metres or more; |
k) |
the bulk transportation of sewage and water, including storm water, in pipelines with— |
i) |
an internal diameter of 0,36 metres or more; or |
ii) |
a peak throughput of 120 litres per second or more; |
l) |
the transmission and distribution of electricity above ground with a capacity of more than 33 kilovolts and less than 120 kilovolts; |
m) |
any purpose in the one in ten year flood line of a river or stream, or within 32 metres from the bank of a river or stream where the flood line is unknown, excluding purposes associated with existing residential use, but including- |
n) |
the off-stream storage of water, including dams and reservoirs, with a capacity of 50 000 cubic metres or more, unless such storage falls within the ambit of the activity listed in item 6 of Government Notice No. R.387 of 2006; |
o) |
the recycling, re-use, handling, temporary storage or treatment of general waste with a throughput capacity of 20 cubic metres or more daily average measured over a period of 30 days, buts less than 50 tons daily average measured over a period of 30 days; |
p) |
the temporary storage of hazardous waste; |
q) |
the landing, parking and maintenance of aircraft including- |
i) |
helicopter landing pads, excluding helicopter landing facilities and stops used exclusively by emergency services; |
ii) |
unpaved aircraft landing strips shorter than 1,4km; |
iii) |
structures for equipment and aircraft storage; |
iv) |
structures for maintenance and repair; |
v) |
structures for fuelling and fuel storage; and |
vi) |
structures for air cargo handling; |
r) |
the outdoor racing of motor powered vehicles including— |
s) |
the treatment of effluent, wastewater or sewage with an annual throughput capacity of more than 2 000 cubic metres but less than 15 000 cubic metres; |
t) |
marinas and the launching of watercraft on inland fresh water system;s |
u) |
above ground cableways and funiculars; |
v) |
advertisements as defined in classes 1(a), 1(b), 1(c), 3(a), 3(b), 3(l) of the South African Manual for Outdoor Advertising Control. |
|
The competent authority in respect of the activities listed in this part of the schedule is the environmental authority in the province in which the activity is to be undertaken unless it is an application for an activity contemplated in section 24C(2) of the Act, in which case the competent authority is the Minister or an organ of state with delegated powers in terms of section 42(1) of the Act, as amended.
|
2
|
Construction or earth moving activities in the sea or within 100 metres inland of the high water mark of the sea, in respect of—
a) |
facilities for the storage of material and the maintenance of vessels; |
b) |
fixed or floating jetties and slipways; |
|
|
3
|
The prevention of the free movement of sand, including erosion and accretion, by means of planting vegetation, placing synthetic material on dunes and exposed sand surfaces within a distance of 100 metres inland of the high-water mark of the sea.
|
|
4
|
The dredging, excavation, infilling, removal or moving of soil, sand or rock exceeding 5 cubic metres from a river, tidal lagoon, tidal river, lake, in-stream dam, floodplain or wetland.
|
|
5
|
The removal or damaging of indigenous vegetation of more than 10 square metres within a distance of 100 metres inland of the high-water mark of the sea
|
|
6
|
The excavation, moving, removal, depositing or compacting of soil, sand, rock or rubble covering an area exceeding 10 square metres in the sea or within a distance of 100 metres inland of the high-water mark of the sea.
|
|
7
|
The above ground storage of a dangerous good, including petrol, diesel, liquid petroleum gas or paraffin, in containers with a combined capacity of more than 30 cubic metres but less
|
|
8
|
|
The competent authority for this part of the schedule is the Minister or an organ of state with delegated powers in terms of section 42(1) of the Act, as amended.
|
9
|
|
10
|
|
The competent authority in respect of the activities listed in this part of the schedule is the
environmental authority in the province in which province in which the activity is to be undertaken unless it is an application for an activity contemplated in section 246(2) of the Act, in which case the competent authority is the Minister or an organ of state with delegated powers in terms of section 42(1) of the Act, as amended.
|
11
|
|
12
|
The transformation or removal of indigenous vegetation of 3 hectares or more or of any size where the transformation or removal would occur within a critically endangered or an endangered ecosystem listed in terms of section 52 of the National Environmental
Management: Biodiversity Act, 2004 (Act No. 10 of 2004),
|
13
|
The abstraction of groundwater at a volume where any general authorisation issued in terms of the National Water Act, 1998 (Act No. 36 of 1998) will be exceeded.
|
14
|
The construction of masts of any material or type and of any height, including those used for telecommunication broadcasting and radio transmission, but excluding—
a) |
masts of 15 metres and lower exclusively used— |
ii) |
for lighting purposes |
c) |
lightning conductor poles. |
|
15
|
The construction of a road that is wider than 4 metres or that has a reserve wider than 6 metres, excluding roads that fall within the ambit of another listed activity or which are access roads of less than 30 metres long.
|
16
|
The transformation of undeveloped, vacant or derelict land to—
a) |
establish infill development covering an area of 5 hectares or more, but less than 20 hectares; or |
b) |
residential, mixed, retail, commercial, industrial or institutional use where such development does not constitute infill and where the total area to be transformed is bigger than 1 hectare |
|
17
|
Phased activities where any one phase of the activity may be below a threshold specified in this Schedule but where a combination of the phases, including expansions or extensions, will exceed a specified threshold.
|
18
|
The subdivision of portions of land 9 hectares or larger into portions of 5 hectares or less.
|
19
|
The development of a new facility or the transformation of an existing facility for the conducting of manufacturing processes, warehousing, bottling, packaging, or storage, which, including associated structures or infrastructure, occupies an area of 1 000 square metres or more outside an existing area zoned for industrial purposes.
|
|
20
|
The transformation of an area toned for use as public open space or for a conservation purpose to another use.
|
21
|
The release of genetically modified organisms into the environment in instances where assessment is required by the Genetically Modified Organisms Act, 1997 (Act No. 15 of 1997) or the National Environmental Management: Biodiversity Act, 2004 (Act No. 10 of 2004).
|
22
|
The release of any organism outside its natural area of distribution that is to be used for biological pest control.
|
23
|
The decommissioning of existing facilities of infrastructure, other than facilities or infrastructure that commenced under an environmental authorisation issued in terms of the Environmental Impact Assessment Regulations, 2006 made under section 24(5) of the Act and published in Government Notice No. R. 385 of 2006, for—
a) |
electricity generation; |
b) |
nuclear reactors and storage of nuclear fuel; |
c) |
industrial activities where the facility or the land on which it is located is contaminated or .has the potential to be contaminated by any material which may place a restriction on the potential to re-use the site for a different purpose; |
d) |
the disposal of waste; |
e) |
the treatment of effluent, waste water and sewage with an annual throughput capacity of 15 000 cubic metres or more; |
f) |
the recycling, handling, temporary storage or treatment of general waste with a daily throughput capacity of 20 cubic metres or more; or |
g) |
the recycling, handling, temporary storage or treatment of hazardous waste. |
|
24
|
The recommissioning or use of any facility or infrastructure, excluding any facility or infrastructure that commenced under an environmental authorisation issued in terms of the Environmental Impact Assessment Regulations, 2006 made under section 24(5) of the Act and published in Government Notice No. R. 385 of 2006, after a period of two years from closure or temporary closure, for—
a) |
electricity generation; |
b) |
nuclear reactors and nuclear fuel storage; or |
c) |
facilities for any process or activity, which require permission, authorisation, or further authorisation, in terms of legislation governing the release of emissions, pollution, effluent or waste prior to the facility being recommissioned. |
|
25
|
The expansion of or changes to existing facilities for any process or activity, which requires an amendment of an existing permit or license or a new permit or license in terms of legislation governing the release of emissions, pollution, effluent.
|