12. Minimum requirements during the Decommissioning Phase

 

12.1 For the purpose of decommissioning, all organic waste treatment facilities that fall within the scope as described in paragraph 3 of these Norms and Standards must, ninety (90) days prior to commencing with decommissioning of such facility, inform the relevant Competent Authority and provide a decommissioning plan. The following information must, as a minimum, be Included in the decommissioning plan:
12.1.1 Timetable for staged remediation;
12.1.2 Re-vegetation or stabilisation program; and
12.1.3 Proposed post-closure monitoring,maintenance and use.