10. Verification of information

 

(1) If a provincial authority responsible for the management of waste information in that province reasonably believes that the information submitted is incorrect or misleading, a provincial authority as the case may be, may instruct a registered person who the information belongs to, in writing, to—
(a) submit an audit report prepared by an independent person on the accuracy of the information that has been submitted to the Department; or
(b) undertake a waste quantification survey and submit a waste quantification report prepared by an independent person.

 

(2) An audit report or waste quantification report requested in terms of subregulation (1) must be submitted within the period determined by a provincial authority, which period may not be less than thirty (30) days.

 

(3) A registered person is liable for all costs in connection with compliance with an instruction in terms of subregulation (2).

 

(4) If a registered person fails to submit an audit report or waste quantification survey report contemplated in subregulation (2) within the period determined by a provincial authority, a provincial authority may—
(a) appoint an independent auditor/person to perform the audit or waste quantification survey; and
(b) recover the cost of the audit or waste quantification survey from the registered person.