Chapter 4 : Site Inspection Meeting and Submission of Technical Report on Water Use Licence Application

11. Submission of technical report on water use licence application

 

(1) The applicant must, within a period of 105 days of the date of being informed of the required information for compilation of a technical report on water use licence application, as contemplated in regulation 10(3), submit such a report to the responsible authority, including any relevant specialists reports as set out in Annexure D.

 

(2) Failure to submit the required water use licence application technical report within the stipulated timeframe will result in the rejection of the application.

 

(3) Where the application is rejected under sub-regulation (2) the responsible authority must notify the applicant and any other interested and relevant institutions.