Acts Online
GT Shield

Petroleum Products Act, 1977 (Act No. 120 of 1997)

Regulations

Regulations regarding Petroleum Products Site and Retail Licences

Chapter 3 : General Provisions

31. Decision-making by Controller

 

(1) The Controller must make any decision required to be made by the Controller in these Regulations, within a period of 90 days: Provided that—
(a) in the case of an application for a licence by an applicant in respect of whom section 2D of the Act is applicable, the period commences from the date of acceptance of the application;
(b) in the case of an application for a licence by an applicant in respect of whom section 2D of the Act is not applicable, the period must commence from the date of receipt of the proof of publication of the notice contemplated in regulation 4(5) and regulation 16(5); and
(c) in the first six months after the commencement of these Regulations, the period is 250 days.