6. Evaluation of a manufacturing licence application

 

(1) In evaluating an application for any manufacturing licence, the Controller must, subject to subregulation (2) verify that—
(a) the information and the documents submitted with the application form are true and correct; and
(b) the notice contemplated in regulation 4(1) was published.

 

(2) In the case of application by a person in respect of whom section 2D of the Act is not applicable, the Controller must be satisfied that—
(a) except in the case of an application for a facility manufacturing biofuels, there is a need for additional capacity; and
(b) must comply with section 2B(2) of the Act.