Promotion of Administrative Justice Act, 2000 (Act No. 3 of 2000)7. Procedure for judicial review |
1) | Any proceedings for judicial review in terms of section 6(1) must be instituted without unreasonable delay and not later than 180 days after the date- |
a) | subject to subsection (2)(c), on which any proceedings instituted in terms of internal remedies as contemplated in subsection (2)(a) have been concluded; or |
b) | where no such remedies exist, on which the person concerned was informed of the administrative action, became aware of the action and the reasons for it or might reasonably have been expected to have become aware of the action and the reasons. |
2) |
a) | Subject to paragraph (c), no court or tribunal shall review an administrative action in terms of this Act unless any internal remedy provided for in any other law has first been exhausted. |
b) | Subject to paragraph (c), a court or tribunal must, if it is not satisfied that any internal remedy referred to in paragraph (a) has been exhausted, direct that the person concerned must first exhaust such remedy before instituting proceedings in a court or tribunal for judicial review in terms of this Act. |
c) | A court or tribunal may, in exceptional circumstances and on application by the person concerned, exempt such person from the obligation to exhaust any internal remedy if the court or tribunal deems it in the interest of justice. |
3) | The Rules Board for Courts of Law established by section 2 of the Rules Board for Courts of Law Act, 1985 (Act No. 107 of 1985), must, before 28 February 2009, subject to the approval of the Minister, make rules of procedure for judicial review. |
4) | Until the rules of procedure referred to in subsection (3) come into operation, all proceedings for judicial review under this Act must be instituted in a High Court or another court having jurisdiction.. |
5) | Any rule made under subsection (3) must, before publication in the Gazette, be approved by Parliament. |